Schedule of Values
Highrise Development
Schedule of Values Items
5 items| Item # | Description | Scheduled Value | Change Order | Actions |
|---|---|---|---|---|
| 01000 | General Conditions | $350,000.00 | Original Scope | |
| 02100 | Site Preparation | $210,000.00 | Original Scope | |
| 03100 | Concrete Foundations | $560,000.00 | Original Scope | |
| 04200 | Masonry | $425,000.00 | Original Scope | |
| 05100 | Structural Steel | $780,000.00 | Original Scope |